Lecture 14, 23.01.2025 Additional test
You have 30 min.
Select the tool you find the best for solving the problem described below. Prepare calculations and the source file with your calculation upload as a solution (the calculation of the quantities must be described understandably).
You have to calculate the costs of finishing materials for the developer. In the multi-family house are 10 identical flats. Each flat consisted of:
- Kitchen (floor: 4x2 m, terracotta; walls: 50% terracotta and 50% paint, ceiling: paint)
- Bathroom (floor: 4x2 m, terracotta; walls: terracotta; ceiling: paint)
- Bedroom x3 (floor: 4x4 m, floor panels; walls: paint; ceiling: paint)
- Corridor (floor: 4x2 m, terracotta; walls: paint, ceiling: paint)
The floor height is 3 m. Calculate the amount of required material for one flat and the whole house as well as the total cost for a single flat and the house, knowing the prices of surface finishes:
- paint 30 PLN/m2
- terracotta 150 PLN/m2
- floor panels 100 PLN/m2